Substation transformer replacement planning
The aging transformers at the Bishop, Poe, and Gipsy substations need replacing, but new units may take six years or longer to manufacture. Planning is starting now so reliability isn't compromised down the road.
Poe/Mercer Pump Station screen replacement
Council approved a funding agreement with the state loan programs to design and build replacement screens at the Poe/Mercer Pump Station — upkeep of the wastewater system.
PowerBlock voltage conversion project
A new ordinance would let the Utilities Director contract with PowerSecure, Inc. for the PowerBlock Voltage Conversion Project — introduced on first reading.
Evergreen Terrace Gas Service Upgrade Easement
Council granted Columbia Gas an easement on an emergency basis so the Evergreen Terrace gas service upgrade can move forward without delay.
Stormwater flooding at W. Merry Ave. and Fairview Ave.
A resident says heavy rains flood her driveway six feet deep at the corner of West Merry and Fairview. City officials promised to share results of utility camera inspections of the storm pipes and any corrective actions.